|
Project Portfolio
|
 |
|
|
| | | |
|
|
BART Extension
To San Francisco Airport – Line Contract
San Francisco
Peninsula, CA
 |
The BART Extension to the San Francisco Airport is a major
subway project which, when completed, will connect the
existing BART system to the San Francisco Airport and extend
the system as far south as Millbrae, California. A large
portion of the new subway alignment is adjacent to the
existing PCJPB (Caltrain) commuter rail line. Berti-Lindquist
is providing the PCJPB with independent design review of
temporary and permanent structures that are within the
influence of the Caltrain railroad tracks. The reviews
include the temporary excavation shoring (deep sheet pile
and soil-mix wall cofferdams below the water table and
adjacent to the railroad tracks), as well as the design
criteria and detailed designs of the permanent subway
cut-and-cover structures that are being constructed adjacent
to, and in some places beneath, the PCJPB tracks.
Owner Bay Area Rapid Transit District (BART) |
Client Peninsula Corridor Joint Powers Board (PCJPB)
|
|
|
Golden Gate Bridge - Seismic
Retrofit (Phase II) - South Approach Structures
San Francisco, CA
 |
Analysis of Existing Structures for Temporary Construction
Conditions, Temporary Trestle & Excavation Shoring
This $120+ million project involves the complete retrofit of
all the South Approach Structures to the Golden Gate Bridge.
Berti-Lindquist has been retained by the general contractor
to analyze existing structures for temporary construction
conditions and loading, as well as to design miscellaneous
temporary facilities including excavation shoring and a
trestle for heavy equipment. Engineering assignments to date
include the design of protection for an existing historic
seawall, the temporary support of a portion of the roof and
a wall of the South Anchorage Housing when the supporting
columns and foundations for these structures are removed,
and the excavation shoring required to retrofit the
existing foundations of the South Approach Structures.
Owner Golden Gate Bridge District | Client Shimmick Obayashi, JV |
|
|
San Onofre Nuclear
Generating Station – Demolition of Roof of Sphere Enclosure
Building,
Demolition Engineering
San Clemente, CA
|
 |
Berti-Lindquist is providing detailed demolition engineering
for Cleveland Wrecking Company for the removal of the
concrete and steel cone-shaped roof of the sphere enclosure
building at San Onofre Nuclear Generating Station. This
demolition work is part of the decommissioning of the Unit 1
Reactor at the power plant. The enclosure building that
surrounds the steel spherical containment vessel is a thick,
heavily-reinforced concrete cylinder with an insider
diameter of 145 feet. The concrete and steel enclosure roof
structure rises to a height of about 95 feet above the
ground surface at a slope of 1 vertical to 3 horizontal.
Engineering assignments include analyses of the structure at
various stages of roof removal with demolition equipment
operating on the partially demolished roof structure.
Owner
Edison | Client Cleveland Wrecking Company |
|
|
Mallard Slough Pump Station and Pipeline Pump Station
Cofferdam & Temporary Shoring for
Jacking and Receiving Pits
Baypoint, California
|
 |
Working for the general contractor, Lindquist and Berti
designed a sheet pile cofferdam for a new pump station at
Mallard Slough. The pump station projects into Mallard
Slough from an existing levee underlain by soft organic
clays and peat. The cofferdam sheets are supported by
combination of a sheet pile deadman on the landward side to
resist significant unbalanced loading from the existing
levee together with a single level of cross-lot bracing. The
depth of excavation was approximately 30 feet. Developed an
alternative sequence for the pump station that reduced the
construction cost as well as risks associated with the
contract-specified scheme. Also, designed solidor pile and
lagging shoring for jacking and receiving pits for the three
pipe jacking locations.
Owner Contra
Costa Water District | Client Homer J. Olsen, Inc. |
|
|
Vasona Light Rail Project -
Contract C345 - San Jose Diridon Tunnels
Temporary Structures (Excavation Shoring & Bridges)
San Jose, California
Description: The project consists of the construction of
1500 feet of the VTA’s light rail system, including approach
channels, a subway section, and an extension for an existing
pedestrian tunnel. The project is located in downtown San
Jose, adjacent to the San Jose Arena. The subway and
pedestrian tunnel extension cross the main Diridon Station
rail yard (twelve tracks). As subconsultants working for the
project structural engineer, Lindquist and Berti provided
detailed design of the temporary shoring for excavations up
to 30 feet deep required for construction of the reinforced
concrete boxes and channels. The shoring system consists of
soldier pile reinforced deep-soil-mix wall supported by
cross-lot bracing. A temporary rail bridge and platform were
also designed to maintain rail traffic and platform access
across the open subway excavation.
Owner Santa Clara Valley Transportation Authority (VTA)
|
Client Biggs Cardosa & Associates
|
|
Moss Landing
Power Plant Stack Demolition Engineering
Moss Landing, California
|
 |
Berti-Lindquist is providing demolition engineering
for the Cleveland Wrecking Company for the removal
of eight 225-foot high stacks at the Moss Landing
Power Plant, near Monterey, California. Berti-Lindquist
has prepared drawings and computations indicating
that it is acceptable to remove the lateral members
that brace six of the eight stacks prior to
demolition. BLCE has also provided details of
reinforcement for new openings being cut in the
bases of the stacks to permit removal of materials
from inside.
Client Cleveland Wrecking Company | Owner
Duke Energy
|
|
|
|
Copyright
© 2011 All Rights Reserved | e-mail us
| (925)-247-9000
Berti-Lindquist Consulting Engineers, A Division of Brierley Associates | 920
Country Club Drive, Suite 2A |
Moraga, CA 94556 | |